Categories
Uncategorized

Verizon OC-12 Up, Construction Update

IMAG0040The Verizon OC-12 circuit is now up and running. They’re still working on provisioning the circuit and bringing the diverse links to the Overture up. From there we’ll take an Ethernet handoff.

We’re slightly behind schedule with the city of Reno taking two months to issue a permit for minor changes; we had expected to be able to start moving in and preparing the space for our equipment on the 15th, and the contractor just started this morning. Now we’re expecting to start moving the first week of August.