New Facility Progress #4

Although we are still missing the UPS (now due to arrive on Sept. 16), we did receive the paralleling tie cabinet and started installing the wiring troughs in the server room that will carry the overhead electrical in the server room. They will eventually be installed overhead, but they’re pictured here laid out on the floor to ensure all the bits and pieces that make them up are accounted for and assigned a position in the installation. The paralleling cabinet will feed a distribution panel and provides an isolated bypass point for the UPS cluster via the large 350A breaker. We’ve also included an updated picture of the telco room.

P9110075 P9110078

P9110080

Unfortunately it doesn’t look like we will be able to meet our October 1 target, although we will have as much completed as there is to work with. At Roller Network, we pride ourselves on quality of work and we will not take shortcuts in order to open early.

Categories
IPv6

Verizon Delay

We were able to confirm that the portion of our order that was dropped was the IPv6 service we had originally confirmed back in May. Apparently that part of the order (along with IPv4 BGP) didn’t make it all the way through to implementation and we were set up as statically routed IPv4 only. Obviously this is completely useless to us, so we forwarded the copies of the confirmation from May.

UPDATE: Take #2 on provisioning will take place on September 4 at 0:800 Pacific.

UPDATE 2: No go. Someone didn’t process the change request.

UPDATE 3: The good news is that we’re getting dual-stack IPv4/IPv6. The bad news is that’s why it’s taking so long; they need to move our endpoint from Sacramento, CA to Phoenix, AZ. (This was our original order; dual stack IPv4/IPv6 both with BGP.)

Categories
Announcements

Forums Changes

Effective immediately, we are discontinuing use of the RollerNetSupport group account and opting to use individual accounts from our side.

Categories
Uncategorized

New Facility Progress #3

No pictures for this update, but we do have an updated ETA on our UPS system of September 8. This much later than we had planned for, but we’re still planning on an October opening date. We’re getting a new three-phase Eaton Powerware system that has a whole unit parallel/redundant capability. We’ll certainly take some pictures of it whenever the first pieces arrive.

Our new Verizon circuit is due to be turned up tomorrow as well, and we’re crossing our fingers that they’ll deliver the IPv6 part of our original request working the first time.

UPDATE: The Verizon circuit was not turned up; part of the order as we submitted it back in May 2009 was dropped for unknown reasons and didn’t make it to final implementation.

Categories
Uncategorized

New Facility Progress #2

Since our last update we’ve finished installing the overhead racking and the two-post racks with cable management that will eventually hold routers, switches, and patch panels.

P8230004 P8230006

We’ve since leveled and locked the threaded rod clamps down (the blue tape marks “incomplete” things). There’s one more cross section we need to install between the two post racks and the opposing run to reduce wire distance. We were short one section of ladder rack over the weekend and Graybar was closed. Next up are conduit runs from the second floor telco room which sits above and in front of the two post racks seen in the picture and we’ll start replacing ceiling panels that won’t interfere with ductwork installation.